Delivering Future Transport 2056

There are 300+ initiatives across Greater Sydney and Regional NSW

Greater Sydney Service and Infrastructure Plan (0-10 years)

 

Initiative Current State Status
Expansion of Travel Choices Program This is an ongoing program that to date has worked with over 850 businesses and organisations across Sydney.
It has contributed to a significant decrease in vehicles entering the CBD and an increase in public transport trips during the morning peak.
Program site
In progress
Point to Point Assistance Package All 1,258 applications for additional assistance have now been determined.
Program site
Complete
Road Classification Review A key next step will be the establishment of an independent panel to oversee the review. In progress
Trial of on-demand bus services on selected local bus routes Since the pilot services commenced in October 2017, 22 pilots have been rolled out across Sydney and regional NSW, delivering more than 645,000 customer journeys.
Project site
In progress
Sydney Growth Trains (part of the More Trains, More Services program) All 24 trains of the initial Waratah Series 2 fleet are now in passenger service.
In February 2019, the NSW Government announced the procurement of an additional 17 Waratah Series 2 trains bringing the total of new Waratah Series 2 trains to 41.
In progress
Introduction of higher frequency public transport services on selected corridors Sydney Metro North West opened in May 2019.
Project site
The More Trains, More Services program has introduced 1,500 additional weekly services across the rail network since 2017.
Project site
In progress
Cycling and pedestrian infrastructure Cycling infrastructure is being delivered across the State through the Priority Cycleways Program, the Cycling Towns Program and the Connecting Centres Cycling Partnership Program.
Program site
Investigation into walking infrastructure has commenced.
In progress
Council Partnership Program to improve local walking and cycling connections Councils are eligible to apply for funding under the Walking and Cycling Program.
Program site
All place plans are being co-designed with councils and are considering walking and cycling connections.
In progress
Bus Priority Infrastructure Program This is an ongoing ten year program with multiple projects underway.
Program site
In progress
New and replacement buses The 2019/2020 financial year Major Bus order for the State Transit Authority has been placed. In progress
Transport Access Program (Improve access to train stations and ferry wharves) This is an ongoing program with multiple projects in the planning and delivery stages.
The 2019 State Budget allocated an additional $885 million over four years to upgrade additional ferry wharves and 68 train stations.
Program site
In progress
Public transport passenger service improvements Infrastructure upgrades (including passenger information, CCTV and platform upgrades) have commenced.
Procurement for buses in metro and outer metro areas now includes improved customer information and CCTV.
In progress
Pinch Point Program This is on track for completion in June 2021, with 212 existing projects and initiatives and a further 60 projects underway.
Project site
In progress
Safer Roads Program This is an ongoing program of road safety infrastructure projects.
$373 million is being invested over four years to improve road safety, including continuing investment under the Road Safety Plan 2021
Program site
In progress
New Intercity Fleet The first trains arrived in Australia in December 2019 and remaining trains will arrive progressively from early 2020.
All trains will undergo rigorous testing before entering passenger service.
Enabling and maintenance facility works are underway.
Project site
In progress
Identification and protection of corridors for future transport links Consultation on four corridors was held in 2018.
Review and assessment of more than 6,000 submissions is progressing.
Project site
In progress
Greater Sydney Parking Guideline These are currently being considered as part of strategic approach for access to centres and interchanges. In progress
Implementation of the Movement and Place Framework Transport for NSW and the Government Architect NSW are working collaboratively to develop a movement and place framework.
A draft practitioners' toolkit is currently under development.
Project site
In progress
Road Space Allocation Policy Policy development is underway to support the efficient movement of people and goods along corridors. In progress
Last Mile Freight Policy The Freight and Ports Plan 2018-2023, which was released in September 2018, considers last mile freight issues.
A Last Mile Freight Innovation Challenge was launched in May 2019 with successful entrants expected to commence trials in December 2020.
Project site
In progress
Innovative walking and cycling initiatives An active transport to schools program is currently being developed.
A safety initiative was launched in July 2018 which allows children under 16 to ride on the footpath.
Program site
In progress
Road network planning and safety development strategies Actions were included in the Road Safety Plan, which was released in February 2018. In progress
Integrated active transport policies to support long-term integrated transport and land use planning Councils are eligible to apply for funding under the Walking and Cycling Program.
Program site
All place plans are being co-designed with councils and consider walking and cycling connections.
In progress
Policy and regulation for Assisted Mobility Devices (AMDs) Work is underway to develop a policy and regulatory framework to manage the safe introduction and promotion of Assisted Mobility Devices. In progress
Policy and regulation for Connected and Automated Vehicles (CAVs) The Connected and Automated Vehicle (CAV) Plan was released in January 2019.
Project site
Policy and regulatory issues are also being considered through a number of CAV trials to be delivered in partnership with industry, researchers, local councils and businesses.
Project site
In progress
Initiatives to further incentivise more customers to travel in off-peak periods The Travel Choices Program aims to encourage customer behavioural change, including choosing to travel outside the peaks.
Program site
In progress
Mobility as a Service (MaaS) implementation The MaaS Innovation Challenge launched in June 2018 and
five pilots are underway.
Project site
MaaS data-sharing specification has been developed and is available on the Project site.
In progress
Trial of artificial intelligence applications Transport for NSW is investigating how data science, supported by applications such as artificial intelligence, can improve customer experience and create an intelligent transport network.
Project site
In progress
Implementation of the Bus Head Start Program Being delivered under the Bus Priority Infrastructure Program. In progress
Service changes to connect to new train lines Bus network enhancement projects are ongoing and include the Government’s Growth Services Program, which provides funding for new or additional services across the bus network, to improve connections with the rail network. In progress
New services on key routes Sydney Metro North West opened in May 2019.
Project site
From April 2019 enhanced service frequency provided from Chatswood into Eastern Harbour CBD.
The More Trains, More Services program has introduced 1,500 additional weekly services across the rail network since 2017.
Project site
In progress
Metropolitan Interchange Program Program currently in planning phase. In progress
Higher frequency public transport services Sydney Metro North West opened in May 2019.
Project site
From April 2019 enhanced service frequency provided from Chatswood into Eastern Harbour CBD.
The More Trains, More Services program has introduced 1,500 additional weekly services across the rail network since 2017.
Project site
In progress
Trial of on-demand ferry services on Sydney Harbour In October 2019, the Bays Precinct on-demand ferry trial commenced.
Project site
In progress
Centres and Placemaking Enhancement Package Place-based transport strategies for Liverpool, Penrith and South-East Sydney are being prepared to support local activity and improve walking and cycling. In progress
Cycling improvements around metropolitan and strategic centres and on the Principal Bicycle Network Consultation underway with stakeholders to develop the Principal Bicycle Network. In progress
Walking improvements around metropolitan and strategic centres Councils are eligible to apply for funding under the Walking and Cycling Program.
Program site
All place plans are being co-designed with councils and consider walking and cycling connections.
In progress
Bus priority access program for centres An ongoing 10 year program with multiple projects underway.
Program site
In progress
Precinct Improvement Program Active Transport is being considered in the development of a strategic approach for accessing centres and interchanges. In progress
More Trains, More Services program Stage 1 (Metro Integration Service Adjustment) was delivered in April 2019
Transport for NSW is now seeking feedback on the Review of Environmental Factors (REF) for upgrade works on theT4 Illawarra, T8 Airport and South and the South Coast lines.
Project site
In progress
Roll-out of electric vehicle (EV) charge points EV charging program is recommended in the Electric and Hybrid Vehicle Plan.
$5 million has been committed to co-deliver EV charging points with industry and local government.
Electric and Hybrid Vehicle Plan
In progress
Bus priority infrastructure to support new services Ongoing 10 year program with multiple projects underway.
Program site
In progress
Investment in Smart Roads The M4 Smart Motorway Project is being delivered in stages and scheduled for completion in 2020.
Project site
In progress
'Pedestrian Safe System' Program Multiple pedestrian safety initiatives are being delivered under the Road Safety Plan 2021. In progress
Expanded 40km/h High Pedestrian Activity Area Program Expansion includes areas around Ultimo, Barangaroo, Dawes Point, Millers Point and the Eastern Harbour CBD.
Project site
Complete
Sydney Metro Northwest Sydney Metro Northwest opened in May 2019. Complete
Sydney Metro City & Southwest Early works are underway on the Chatswood to Sydenham rail line.
Planning approval was received in December 2018 to upgrade the T3 Line between Sydenham and Bankstown.
Project site
In progress
Northern Beaches B-Line B-Line has been operational since November 2017 and all critical works were completed on schedule by December 2018.
Project site
Complete
CBD & South East Light Rail CBD & South East Light Rail Stage 1 between Circular Quay and Randwick via Central Station opened in December 2019.
Stage 2 between Circular Quay and Juniors Kingsford via Central Station is scheduled to open in March 2020.
Project site
In progress
Northern Beaches Hospital road upgrade Excavation and construction are underway for Warringah Road underpass and bridges, Hilmer Street Bridge, Forest Way and Wakehurst Parkway.
Project site
In progress
Sydney Airport road upgrades Sydney Airport West, Marsh Street widening, and Sydney Airport East, Wentworth Avenue are open to traffic.
Sydney Airport North, O'Riordan Street is under construction.
Project site
In progress
Priority Cycleway links in inner Sydney Consultation is underway with stakeholders to develop a Principal Bicycle Network.
Cycling infrastructure is being delivered across the State through the Priority Cycleways Program, the Cycling Towns Program and the Connecting Centres Cycling Partnership Program.
Program site
In progress
Macquarie Park Interchange and precinct improvements Currently in the concept design phase, which is planned for completion in early 2020.
 
In progress
Ferry Fleet Replacement Program, including upgraded services on Parramatta River ferries Transdev has been awarded the contract to continue the operation of Sydney Ferry services for the next nine years.
At least ten new Parramatta River Class ferries will be ordered to provide additional capacity.
In progress
Parramatta Road public transport improvements Short term works to improve bus and traffic reliability along the Burwood to Haberfield section of Parramatta Road are being finalised.
Project site
Other improvements are being considered as part of integrated network planning.
In progress
Western Harbour Tunnel and Beaches Link Environmental Impact Statement for the Western Harbour Tunnel and Warringah Freeway upgrade released for consultation in November 2019.
The Proposed Reference Design for the Beaches Link released in November 2019.
Project site
In progress
F6 Extension Stage 1 WestConnex to President Ave, Kogarah Stage 1 received planning approval in December 2019.
Construction is expected to begin in early 2022 and the road open to motorists by the end of 2025.
Project site
In progress
F6 Extension - Kogarah to Loftus Not commenced. Not commenced
Harbour CBD to Green Square mass transit link Not commenced.
Improvements being considered as part of integrated network planning.
Not commenced
Green Square to La Perouse rapid bus link Not commenced.
Improvements being considered as part of integrated network planning.
Not commenced
Eastern Suburbs to Inner West rapid bus links Not commenced.
Improvements being considered as part of integrated network planning.
Not commenced
Improved bus services between Northern Beaches and Chatswood Additional route E60 services are being introduced in 2020 as part of 2019-20 Growth Services Program. In progress
Inner Sydney Regional Bike Network within 10km of the Harbour CBD Consultation is underway with stakeholders to develop a Principal Bicycle Network.
Cycling infrastructure is being delivered across the State through the Priority Cycleways Program, the Cycling Towns Program and the Connecting Centres Cycling Partnership Program.
Program site
In progress
East-west public transport connection from Mona Vale to Macquarie Park Delivery date for new services on corridor to be determined. In progress
Sutherland to Cronulla Active Transport Link Stage 1 is under construction and is scheduled for operation by early 2020.
Stage 2 is in the planning phase.
Project site
In progress
Northern Sydney Freight Corridor Stage 2 Being delivered under Stage 4 of the More Trains More Services to enable identification and delivery of joint freight and passenger benefits.
Project site
In progress
Heathcote Road improvements Heathcote Road Intersection improvement at Heathcote Road and Princes Hwy and Heathcote Road are open to traffic.
Other upgrades are in progress.
Project site
In progress
Additional cruise ship capacity The Port Authority is investigating options for additional cruise capacity at two potential sites in Port Botany. In progress
Foreshore Road upgrade Precinct Planning will be considered in conjunction with a broader range of development that is currently being planned within the area.
Scope and extent of State and federally funded work from Port Botany to Mascot Airport is under investigation.
In progress
Duplication of Port Botany freight rail line In planning stage and being considered in line with Sydney Gateway project.
Project site
In progress
WestConnex Stage 1B (new M4 tunnels) opened to traffic in July 2019.
Stage 2 (New M5) is due to open in 2020.
Project site
In progress
NorthConnex It is expected to open to traffic in 2020.
Project site
In progress
Victoria Road public transport improvements Short term improvements are under development.
Other improvements being considered as part of integrated network planning.
In progress
Parramatta Light Rail Stage 1 Detailed design, enabling works and site investigations across the alignment are in progress.
Construction is scheduled to finish in march 2022.
Construction scheduled to finish in March 2022.
Project site
In progress
Priority cycleway links in the Central River City Consultation is underway with stakeholders to develop a Principal Bicycle Network.
Cycling infrastructure is being delivered across the State through the Priority Cycleways Program, the Cycling Towns Program and the Connecting Centres Cycling Partnership Program.
Program site
In progress
Sydney Metro West Strategic station options finalised after consultation on Pyrmont and Rydalmere stations  in late 2019.
Construction work expected to commence in 2020.
In progress
Parramatta Light Rail Stage 2 In planning phase.
Project site
In progress
Parramatta to Bankstown to Hurstville/Kogarah rapid bus link This is being considered as part of integrated network planning. In progress
Improved bus services between north of Parramatta and centres to the south of Parramatta This is part of an ongoing regular network development. In progress
Parramatta inner ring road (improvements to existing surface roads) Not commenced. Not commenced
T-Way to T-Way link This is being considered as part of integrated network planning. In progress
Safe cycleway network within 10km of Parramatta Consultation is underway with stakeholders to develop a Principal Bicycle Network.
Cycling infrastructure is being delivered across the State through the Priority Cycleways Program, the Cycling Towns Program and the Connecting Centres Cycling Partnership Program.
Program site
In progress
Western Sydney Infrastructure Plan, including the new M12 Two Northern Road and Bringelly Road projects are open to traffic and another six are in construction.
Werrington Arterial Road and Glenbrook intersection is open to traffic.
M12 is in planning stage.
Local Road package is progressing.
Project site
In progress
Priority Cycleway links in the Western Parkland City Consultation is underway with stakeholders to develop a Principal Bicycle Network.
Cycling infrastructure is being delivered across the State through the Priority Cycleways Program, the Cycling Towns Program and the Connecting Centres Cycling Partnership Program.
Program site
In progress
M4 Smart Motorway The M4 Smart Motorway Project is being delivered in stages and scheduled for completion in 2020.
Project site
In progress
Western Sydney Growth Roads Program Ongoing program with multiple projects, mostly in the construction stage. In progress
Access to Moorebank Intermodal Terminal Development work is underway. In progress
North-south rail link in Western Parkland City: St Marys – WSA-Badgerys Creek Aerotropolis Transport links to connect the emerging Western Parkland Sydney and new Western Sydney Airport are being investigated as part of the planning process and through broader integrated network planning. In progress
North-south rail link in Western Parkland City: Cudgegong Rd - St Marys Transport links to connect the emerging Western Parkland Sydney and new Western Sydney Airport are being investigated as part of the planning process and through broader integrated network planning. In progress
North-south rail link in Western Parkland City: WSA-Badgerys Creek Aerotropolis – Campbelltown-Macarthur Transport links to connect the emerging Western Parkland Sydney and new Western Sydney Airport are being investigated as part of the planning process and through broader integrated network planning. In progress
Leppington to WSA-Badgerys Creek Aerotropolis rail link Transport links to connect the emerging Western Parkland Sydney and new Western Sydney Airport are being investigated as part of the planning process and through broader integrated network planning. In progress
Improved services on the Richmond Line In planning stage as part of More Trains More Services Stage 4. In progress
WSA-Badgerys Creek Aerotropolis-Parramatta rail link Transport links to connect the emerging Western Parkland Sydney and new Western Sydney Airport are being investigated as part of the planning process and through broader integrated network planning. In progress
Infrastructure to support rapid bus connections and improved bus connections between WSA-Badgerys Creek Aerotropolis and Penrith, Liverpool, Blacktown and Campbelltown-Macarthur Transport links to connect the emerging Western Parkland Sydney and new Western Sydney Airport are being investigated as part of the planning process and through broader integrated network planning. In progress
Western Parkland City bus interchange Transport links to connect the emerging Western Parkland Sydney and new Western Sydney Airport are being investigated as part of the planning process and through broader integrated network planning. In progress
WSA-Badgerys Creek Aerotropolis CAV zone Not commenced. Not commenced
Western Sydney Fuel Pipeline A multi-agency approach is being developed. In progress
Southern Sydney Freight Line improvements Work is being delivered by The Australian Rail Track Corporation (ARTC). 
Pending planning approval, construction is expected to start in 2020.
In progress
Upgrade to Blue Mountains Line Blue Mountains Route Clearance Work is progressing. In progress
Picton Road Safety Improvements Installed new median safety barriers, widened centre lines and Audio Tactile Line Marking (ATLM).
Additional road safety improvements are in the planning stage.
Project site
In progress
Appin Road Upgrade Commenced investigation of options to improve safety, widening and intersections improvements, including the provision of additional capacity, Audio Tactile Line Marking (ATLM), a widened centreline treatment, and/or median barriers where appropriate.
Project site
In progress
Bells Line of Road Corridor Upgrade Works have commenced to replace Clarence Road rail bridge on Chifley Road with a new bridge. Initial works to upgrade Chifley Road at Scenic Hill are currently underway.
Project site
In progress
Sydney-Canberra Faster Rail (now ‘Fast Rail’) Improvement Land use analysis, demand modelling and economic analysis currently underway for the Southern Inland Route from Sydney to Canberra via Goulburn.
Project site
In progress
Sydney-Central Coast-Newcastle Faster Rail
(now ‘Fast Rail’) Improvement
In 2019, $295 million was allocated over four years to investigate potential routes for a fast rail network. Stakeholder engagement on the Northern Route from Sydney to Newcastle via the Central Coast and activities including options development and assessment, and economic analysis are underway.
Project site
In progress
Sydney-Wollongong Faster Rail (now ‘Fast Rail’) Improvement Activities to investigate Southern Coastal Route including Wollongong and Nowra are being planned.
Project site
In progress
Improved bus connections between South West Sydney and Illawarra Being considered as part of integrated network planning. Not commenced
Passenger train improvements to support growth at Wilton Options to serve growth in the Wilton Growth Precinct are being considered as part of the Fast Rail project.
Project site
In progress

 

 

Regional Service and Infrastructure Plan (0-10 years)

Initiative Current State Status
Road Classification Review Key next step will be the establishment of an independent panel to oversee the review. In progress
NSW Boating Now Program 210 projects have been delivered and 58 projects are underway through partnerships with local councils and other organisations.
Program site
In progress
Regional Rail Fleet Project Procurement is underway for new trains to replace the ageing NSW regional rail fleet.
Detailed service planning activities commenced in July 2019.
Project site
In progress
Safer Roads Program Ongoing program of road safety infrastructure projects, with 180 projects delivered in 2018-19, worth over $70 million.
Program site
In progress
Saving Lives on Country Roads Program An ongoing program to reduce serious injuries and fatalities by addressing high risk curves and fatigue.
Program site
In progress
Local Government Road Safety Program Ongoing program in partnership with local government.
Program site
In progress
Road Freight Safety and Productivity The NSW Heavy Vehicle Access Policy Framework was published in September 2018. In progress
Regional Road Freight Corridor Fund Not commenced. Not commenced
Bridges for the Bush Program An ongoing program to replace and upgrade bridges in regional NSW.
Program site
In progress
Fixing Country Rail Program The program has delivered five out of the ten pilot projects to upgrade parts of the regional rail network.
Program site
In progress
Fixing Country Roads Of the 244 projects to repair and upgrade local and regional roads, 98 have been completed.
Program site
In progress
Transport Access Program An ongoing program with multiple projects in the planning and delivery stage.
2019 State Budget allocated an additional $885 million over four years to upgrade 68 stations.
Program site
In progress
Heavy vehicle rest areas A review of the Heavy Vehicle Rest Area Strategy is being completed.
 
In progress
Transport corridor planning An ongoing program to develop plans for strategically significant corridors across regional NSW. In progress
Regional Passenger Transport Strategic Framework and Delivery Model Not commenced. Not commenced
Hub and Spoke Model Commenced Regional Transport Plans for Illawarra-Shoalhaven, Central Coast and Central West.
Completed Greater Newcastle Future Transport Plan.
In progress
Increase availability of regional slots at Sydney’s airports during peak hours Western Sydney Airport is planned to open in late 2026 and will significantly increase capacity from regional destinations. In progress
Demand responsive transport services Eleven Rural and Regional On-Demand pilot programs are operational.
Patronage continues to grow with more than 52,000 passenger trips delivered to date across the pilots to end August 2019.
Project site
In progress
Country Passenger Infrastructure Grants Scheme 2019-20 scheme underway to provide subsidies to support the construction or upgrade of bus stops across country NSW.
Project site
In progress
First Stop Transport First Stop Transport resource available to help customers plan and access transport and locate information. Complete
Data collection improvements for regional NSW Currently securing access to ongoing NSW wide telecommunications data to analyse regional transport patterns and inform planning. In progress
Regional Airports Program The NSW Government has committed $70 million under the Regional Tourism Infrastructure Fund for upgrades to 27 regional airports.
Program site
Complete
Nelson Bay Road improvements – Fern Bay to Williamtown $275 million has been allocated to improve safety and travel times on Nelson Bay Road including duplicating the road from Williamtown to Bobs Farm and early work to upgrade intersections at Lemon Tree Passage Road and Medowie Road.
Project site
In progress
Newcastle Cruise Terminal Not commenced. Not commenced
Cormorant Road, Industrial Drive to Stockton Bridge (State and Federally Funded) Completed in June 2018.
Project site
Complete
Hunter Pinch Points The Pinch Point Program reduces traffic delays, manages congestion and improves travel times on Hunter's major roads, particularly during weekday peak periods.
Hunter Region traffic improvements.
In progress
New England Highway, Scone Bypass (State and Federally Funded) Construction has started and work is expected to be completed by the end of 2020.
Project site
In progress
New England Highway, Gowrie Gates, Widen Rail Underpass This project was opened to traffic in July 2019.
Project site
Complete
New England Highway, Belford to Golden Highway Upgrade The concept design has been refined and improved in response to community feedback, which was received during the environmental assessment display.
Project site
In progress
Newcastle Inner City Bypass, Rankin Park to Jesmond Construction of a shared path bridge over Newcastle Road at Jesmond commenced in November 2019, ahead of construction of the bypass.
Project site
In progress
New England Highway, Muswellbrook Bypass (Planning) The preferred option for the proposed bypass will be displayed for community feedback in early 2020.
Construction is expected to start in 2022, subject to project approval.
Project site
In progress
New England Highway, Singleton Bypass (Planning) Survey and geotechnical investigations have been completed.
It is now in the concept design and environmental assessment phase.
Project site
In progress
M1, Hexham, Raymond Terrace upgrades Currently in the planning stage.
Project site
In progress
Newcastle Light Rail Construction was completed in November 2018 and services commenced in February 2019.
Project site
Complete
Lower Hunter Freight Corridor Protection Work is underway to preserve the Lower Hunter Freight Corridor to enable a dedicated freight rail line to be constructed between Fassifern and Hexham.
Project site
In progress
Golden Highway Safety and Productivity Works (State and Federally Funded) Work commenced in March 2019 on the Ogilvies Hill and Winery Hill projects.
Other related projects are in the design or planning stage.
Project site
In progress
Pacific Motorway Widening and Reconstruction, Wyong Road to Doyalson Link Road (State and Federally Funded) Work is underway to widen the motorway to provide three lanes in each direction and rebuild the roadway to provide a smoother and more durable surface.
It is expected to be completed in 2020.
Project site
In progress
Pacific Motorway Widening, Kariong Interchange to Somersby Interchange (State and Federally Funded) Work is underway to widen the motorway and upgrade three of the four ramps at the Kariong interchange.
It is expected to be completed in 2020.
Project site
In progress
Pacific Highway, Ourimbah Street to Glen Road Completed in November 2018.
Project site
Complete
Wyong Road, Mingara Drive to Tumbi Road Upgrade Completed in November 2017.
Project site
Complete
Manns Road, Central Coast Highway to Narara Creek Road (Planning) Community consultation undertaken and submissions reports completed in October 2019.
Project site
In progress
Warnervale Link Road, Albert Warner Drive to Pacific Highway (Planning) Feasibility investigations and community consultation have been undertaken. In progress
Pacific Highway, Parsons Road to Ourimbah Street (Planning) Major work commenced in February 2019 to duplicate the Pacific Highway between Ourimbah Street and Parsons Road at Lisarow. In progress
Pacific Highway and Manns Road, Narara Creek Road to Parsons Road (Planning) Community consultation undertaken and submissions reports completed in October 2019.
Project site
In progress
Pacific Highway, Wyong Town Centre (Planning) This is in the planning and pre-construction phase. In progress
Empire Bay Drive, The Scenic Road and Cochrone Street Intersection Upgrade Work has commenced on upgrading the intersection of Empire Bay Drive, The Scenic Road and Cochrone Street. In progress
Kangy Angy Train Maintenance Facility for New Intercity Fleet Construction of the new maintenance facility is underway. In progress
Albion Park Rail Bypass (Planning and Preconstruction) Work has commenced on building an extension of the M1 Princes Motorway between Yallah and Oak Flats to bypass Albion Park Rail. In progress
Nowra Bridge over Shoalhaven River (Planning) (State and Federally Funded) subject to final business case and Federal funding A new four lane bridge over the Shoalhaven River, upgraded intersections and additional lanes on the Princes Highway are in the planning stage.
The Environmental Assessment and Concept Designs were exhibited in August and September 2018.
In progress
Princes Motorway Improvements, Bulli Tops to Picton Road (Planning) (State and Federally Funded) Upgrades to the M1 Princes Motorway between Picton Road and Bulli Tops are in planning stage.
Detailed design work for stage one improvements was completed in April 2019.
In progress
Berry to Bomaderry Upgrade Major work commenced in September 2018 and is scheduled for completion in 2022. In progress
Princes Motorway, Interchange at Base of Mount Ousley (Planning) The project has received planning approval.
The next stage is to prepare the detailed design for the project.
In progress
Burrill Lake Bridge Replacement Completed in March 2018. Complete
MR92 Nerriga Road improvements Work has commenced on upgrading four sections of the road
Stage 1 and 2 are completed.
The full project is expected to be completed by December 2020.
In progress
Bruxner Highway, Replacement Bridge over Clarence River Work is underway for a new Tabulam Bridge over the Clarence River.
The project is expected to be completed by mid-2020.
In progress
Woolgoolga to Ballina (State and Federally Funded) Upgrades to provide 155 kilometres of safer, four-lane divided road are under construction and due for completion in 2020.
Project site
In progress
Warrell Creek to Nambucca Heads (State and Federally Funded) This is completed and was opened to traffic between December 2017 and June 2018. Complete
Summerland Way, Additional Clarence River Crossing (Grafton Bridge) Work is underway to build an additional bridge in Grafton, as well as upgrade parts of the road network in Grafton and South Grafton. In progress
Coffs Harbour Bypass (Subject to final business case & Federal funding) Consultation on the environmental impact  was conducted in September/October 2019.
Project site
In progress
Oxley Highway Safety and Realignment Works (Multi-region) Work has commenced and is expected to be completed by December 2020.
 
In progress
Batemans Bay Bridge (planning) Work has commenced and is expected to be completed in early 2023. In progress
Kosciuszko Road Overtaking Lanes and Safety Improvements Work commenced in December 2018.
Project site
In progress
Barton Highway Improvements (State and Federally Funded) Work has commenced to upgrade the Barton Highway The work has been split into four packages.
Project site
In progress
Queanbeyan Bypass (Ellerton Drive Extension) (State, Federal and Local Government Funded) Construction has commenced with the new road expected to be open in mid-2020. In progress
Eden cruise facilities development Tenders to operate and manage the cruise facility are being assessed. In progress
Monaro Highway Overtaking Lanes and Safety Improvements Completed. Complete
Kings Highway, Replacement Clyde River Bridge Early work was completed in mid-April 2019.
Upcoming activities include ongoing site investigations, utility relocations and further improvements to the design to reduce environmental impacts of the new bridge.
In progress
Main Road 54 (Goulburn to Bathurst) Initial Sealing Completed in April 2018. Complete
Dignams Creek Realignment Completed in April 2019. Complete
Hume Highway Heavy Duty Pavement (State and Federally Funded) Early works commenced in June 2019. In progress
Gocup Road Upgrade Completed in June 2019. Complete
Newell Highway, West Wyalong Heavy Vehicle Bypass
Completed in July 2018.
Complete
Newell Highway Overtaking Lanes (Multi-region) The NSW Government and industry partners are delivering at least 30 additional overtaking lanes on the Newell Highway over 4 years.
Program site
In progress
Cobb Highway, New Bridge at Echuca – Moama The Draft Corridor Plan has been completed and prioritisation of challenges is underway. In progress
Cobb Highway Seal Extension All remaining unsealed sections of the Cobb and Silver City Highways are now in planning or construction.
Project site
In progress
Junee North Triangle Data on traffic volumes, queue length and travel times at key sites along the Princes Highway were collected in June 2019.
Next steps  include conducting analysis, planning and other preparatory work.
In progress
Narrandera – Tocumwal Railway Reactivation Data on traffic volumes, queue length and travel times at key sites along the Princes Highway were collected in June 2019.
Next steps  include conducting analysis, planning and other preparatory work.
In progress
Inland Rail (Federally Funded) Work to deliver an Inland Rail between Melbourne to Brisbane is being led by the Australian Rail Track Corporation (ARTC). In progress
Newell Highway, Mungle Back Creek to Boggabilla Heavy Duty Pavement (State and Federally Funded) Works commenced in November 2018 and included major work on 18 kilometres of new road pavement, 3.5 metre wide lanes in each direction, intersection improvements, widening of road shoulders and the provision of two new overtaking lanes. In progress
New England Highway, Bolivia Hill Upgrade (State,and Federally Funded) Work has commenced, including widening sections of the highway.
 
In progress
Oxley Highway, Gunnedah Bridge over Rail Work has commenced and expected to be completed by mid-2021. In progress
Newell Highway Heavy Vehicle Pavement Upgrades – Narrabri-Moree, North of Moree (Planning) A review of environmental factors has been completed to asses new road pavement, intersection improvements and widening of road shoulders along the Newell Highway, north of Moree. In progress
Barraba Branch Line Not commenced. Not commenced
Tamworth Rail Freight Centre Not commenced. Not commenced
Mitchell Highway, Guanna Hill Realignment Completed October 2018.
Project site
Complete
Newell Highway, Improvements through Coonabarabran (Planning) Currently in the planning stage.
Project site
In progress
Newell Highway, Trewilga Realignment Completed in 2018. Complete
Newell Highway, Parkes Bypass (Planning) Currently in the planning stage.
Project site
In progress
Newell Highway, New Dubbo Bridge (Planning) Currently in the planning stage.
Consultation is being undertaken with local council on design.
Project site
In progress
New Intercity Fleet (Multi-region) The first trains arrived in Australia in December 2019 and remaining trains will arrive progressively from early 2020.
All trains will undergo rigorous testing before entering passenger service.
Enabling and maintenance facility works are underway.
Project site
In progress
Oxley Highway Safety and Realignment Works (Multi-region) Council is delivering the work and it is anticipated to be completed by December 2020. In progress
Regional Rail Maintenance Facility (Dubbo subject to planning approval) Site survey and geotechnical activities commenced in July 2019.
Project site
In progress
Upgrades to Main West Line Stage 1 of the upgrade between Orange and the Blue Mountains for freight and passengers is complete. In progress
Main Road 54 (Goulburn to Bathurst) Initial Sealing Completed April 2018.
Media Release
 
Complete
Regional Transport Plans Commenced Regional Plans for Illawarra-Shoalhaven, Central Coast and Central West.
Completed Greater Newcastle Future Transport Plan.
In progress
Saving Lives on Country Roads program (continuation) An ongoing program to reduce serious injuries and fatalities by addressing high risk curves and fatigue.
Program site
In progress
Local Government Road Safety Program (continuation) An ongoing program in partnership with Local Government.
Program site
In progress
Regional Road Freight Corridor Fund (continuation) Multiple upgrade and bypass projects are in the planning and delivery stages. In progress
Road network management system This involves multiple ongoing projects including the journey planner and livetraffic.com. In progress
CAV Readiness Program Transport for NSW has partnered with industry, researchers, local councils and businesses to develop and co-deliver connected and automated vehicle (CAV) trials in Armidale and Coffs Harbour.
Project site
In progress
Continuation of port efficiency, access and integration initiatives The Cargo Movement Coordination Centre (CMCC)  continues to work on projects for improved efficiency utilising new technology. In progress
Regional booking system A booking system for NSW Train Link services is under development. In progress
Bridges for the Bush continuation This is an ongoing program to replace or upgrade bridges in regional NSW.
Program site
In progress
Place Plans Commenced place plans for Maitland and Wagga Wagga.
Consultation commenced for Port Macquarie and Coffs Harbour place plans.
In progress
Rail Network Optimisation Program Transport for NSW is undertaking planning work to deploy the New Intercity and Regional Fleet. In progress
Towards Zero Infrastructure Program Ongoing Safer Roads Program.
Program site
In progress
Walking programs In the planning stage. In progress
Cycling programs Consultation is underway with stakeholders to develop a Principal Bicycle Network.
Cycling infrastructure is being delivered across the State through the Priority Cycleways Program, the Cycling Towns Program and the Connecting Centres Cycling Partnership Program.
Program site
Not commenced
Car share package To be considered in 2020 as part of regional parking guidelines. Not commenced
Resilience Package An ongoing program of road maintenance and management in regional NSW. In progress
Sealing Country Roads Program In June 2019, the NSW Government announced it will invest $145 million to seal and upgrade the remaining 209 kilometres of the Cobb and Silver City Highways. Around 113.5 kilometres of highway has already been sealed between 2011 and mid-2019.
Project site
In progress
Slopes and culverts condition program Inspections have been undertaken and a plan is in place for completion. In progress
Last Mile Productivity initiatives The Freight and Ports Plan 2018-2023, which was released in September 2018, considers last mile freight issues.
A Last Mile Freight Innovation Challenge was launched in May 2019 with successful entrants expected to commence trials in December 2020.
Project site
In progress
Town Bypasses identification of future need This is being considered as part of regional place plans.
Plans are underway for Maitland, Wagga Wagga, Port Macquarie and Coffs Harbour.
In progress
Implementation of traffic incident and information services A trial with local councils has commenced using Live Traffic NSW. In progress
Inland Port Moorebank Logistics Park commenced operations in November 2019. In progress
Fuel vouchers policy A Regional Seniors Travel pilot program in Coffs Harbour is underway, giving eligible seniors a $250 travel card that can be used for pre-booked NSW TrainLink Regional train and coach services, fuel and taxi trips.
Project Site
In progress
Cross border public transport pricing and regulation MoUs The NSW Cross Border Commissioner is leading initiatives to improve services in cross-border areas. In progress
School Bus and Community Transport Model development The potential for new models of school bus and community transport services and integration with other services is being investigated. In progress
Maritime Safety Program Being delivered under the Maritime Safety Plan 2017-2021. In progress
Active Transport Sharing Scheme Currently under investigation. In progress
Aerial technology use Currently investigating the use of drones for incident management. In progress
Access Prioritisation Plan This is being considered as part of regional place plans.
Plans are underway for Maitland, Wagga Wagga, Port Macquarie and Coffs Harbour.
In progress
Fleet Leasing Policy NSW Electric and Hybrid Vehicle Plan commits to setting a target from 2020/21 for 10 per cent of newly purchased or leased NSW Government vehicles to be electric or hybrid vehicles. In progress
Mobility as a Service (MaaS) The MaaS Innovation Challenge launched in June 2018 and five pilots are underway.
Project site
MaaS data-sharing specification as been developed and is available.
Project site
In progress
Next generation ticketing The rollout of contactless payments is continuing across the network. In progress
Fare alignment The Independent Pricing and Regulatory Tribunal (IPART)’s new fare structure for rural and regional buses has been implemented.
Media Release
Complete
Assisted Mobility Device Strategy TfNSW is engaging with an e-scooter advisory working group to develop conditions for a potential trial. In progress
‘Whole of life’ Approach Plan Work is underway to develop a strategy that re-focuses asset management to adopt a ‘whole of life’ approach. In progress
CAV, electric vehicle and Intelligent Transport System trials The NSW Connected and Automated Vehicle Plan was launched in January 2019. The actions in the Plan are currently being implemented including trials of automated vehicles across metropolitan and regional NSW.
The NSW Electric and Hybrid Vehicle Plan was launched in January 2019. The actions in the Plan are currently being implemented.
In progress
Electric Vehicle Policy The Electric and Hybrid Vehicle Plan has been released and actions in the Plan are currently being implemented. Complete
Newcastle Light Rail network extension Work is underway to evaluate the feasibility of an extension of the Newcastle Light Rail network. In progress
Golden Highway improvements (continuation) A package of upgrades on the Golden Highway between Whittingham and Dubbo is being undertaken, to improve safety, traffic efficiency, network reliability and freight access.
Project site
In progress
M1, Hexham, Raymond Terrace upgrades $5.9 million (State and Federal funding) was allocated in 2019-2020to continue planning for a future extension of the M1 Pacific Motorway to the Pacific Highway at Raymond Terrace.
Project site
In progress
Greater Newcastle Rapid Bus Package Not commenced. Not commenced
Bus headstart for Greater Newcastle Not commenced. Not commenced
Greater Newcastle Place Plans The Greater Newcastle Future Transport Plan was completed in October 2018. Complete
The Lakes Way Corridor Improvements Work is underway to upgrade The Lakes Way through a series of measures, including lane widening, safety measures, intersection improvements at high traffic locations, flood immunity works and asset maintenance works. In progress
Improvements to Newcastle Port The NSW government is working in partnership with the Port of Newcastle as they deliver their master plan. In progress
Nelson Bay Road improvements – Williamtown to Bobs Farm $275 million has been allocated to improve safety and travel times on Nelson Bay Road.
Project site
In progress
Sydney - Central Coast - Newcastle Faster Rail (now ‘Fast Rail’) Improvement In 2019, $295 million was allocated over four years to investigate potential routes for a fast rail network.
Activities including stakeholder engagement, options development and assessment, and economic analysis are underway.
Project site
In progress
Great Dividing Range long term solution study The Connecting the Central West & Orana initiative aims to identify short, medium and long term solutions to improving connectivity for the region.
Preservation of a new corridor is one of the long term options for consideration.
In progress
Great Dividing Range long term solution corridor preservation Corridor preservation will commence once the “Great Dividing Range long term solution study” is closer to completion. Not commenced
M1 – Newcastle SMART Motorway The Strategic Development phase has commenced. In progress
M1 Motorway improvements (Hawkesbury River – Mt White) Not commenced. Not commenced
Bus Headstart for Central Coast Work to be undertaken as needed to develop new bus routes to support new homes as they are built.
 
Not commenced
Central Coast Rapid Bus package Not commenced. Not commenced
Central Coast Place Plans Scoping for preparation of this Place Plan has commenced. In progress
Princes Highway Nowra Bridge replacement In planning stage.
Consultation was undertaken on environmental assessment and concept design.
In progress
Sydney-Wollongong Faster Rail (now ‘Fast Rail’) Improvement Activities being planned to investigate Southern Coastal Route including Wollongong and Nowra.
Project site
In progress
Moss Vale to Unanderra and Coniston Junction rail improvements Not commenced. Not commenced
Picton Rd/ Appin Rd Improvements The Australian and NSW governments are funding two individual projects to improve Appin Road.
Detailed design work is currently underway.
Project site
In progress
Bus headstart for Wollongong Work is to be undertaken as needed to develop new bus routes to support new homes as they are built. Not commenced
Wollongong Place Plans Scoping for preparation of this Place Plan has commenced. In progress
Wollongong Rapid Bus package Not commenced. Not commenced
Bus priority measures on Appin Road Not commenced. Not commenced
Duplication of Princes Highway (Jervis Bay Road Intersection to Moruya), including bypass of Milton-Ulladulla $960 million has been allocated for improving the Princes Highway between Jervis Bay Road and Moruya.
Project site
In progress
Oxley Highway Improvements (North Coast) As part of the $50 million package, major road alignments are now completed including improvements at Rosewood Road and Spencers Cutting and flood immunity works at Hoss Causeway.
New westbound and eastbound overtaking lanes near Keepit Dam have also been completed.
Project site
In progress
Waterfall Way corridor improvements A draft corridor strategy and a route safety review have been completed.
Prioritisation of an integrated program of works is underway for 2019/20+.
Project site
In progress
Tweed Transport Network Plan (encompassing the potential for light rail extension from Gold Coast Airport to Tweed Heads) Work is underway to develop a Tweed Transport Network Plan considering, amongst other initiatives, extension of the current Gold Coast Light Rail project to Tweed Heads. In progress
Bruxner Highway Improvements (Ballina- Casino) Not commenced. Not commenced
Upgrade of Bangalow Road between Bangalow and Lismore Not commenced. Not commenced
Gwydir Highway Improvements (between Grafton and Glen Innes, Jackadgery) Not commenced. Not commenced
Summerland Way Improvements (Grafton-QLD border) Not commenced. Not commenced
Bruxner Highway Improvements (Casino - Tenterfield) Work is underway to improve the Bruxner Highway between Tenterfield and Casino.
Project site
In progress
Moss Vale to Unanderra and Coniston Junction rail improvements Not commenced. Not commenced
Sydney-Canberra Faster Rail (now ‘Fast Rail’) Improvement Land use analysis, demand modelling and economic analysis are currently underway for the Southern Inland Route from Sydney to Canberra via Goulburn.
Project site
In progress
Kings Highway improvements The draft Kings Highway Transport Corridor Plan is currently being prepared.
Project site
In progress
Snowy Mountains Highway improvements (including Brown Mountain) Not commenced. Not commenced
Monaro Highway improvements The draft Corridor Plan has been completed and prioritisation of challenges are underway.
Project site
In progress
Lachlan Valley Way improvements An ongoing program to provide safer and more consistent travelling conditions.
Project site
In progress
Investigate extension of light rail from Canberra to Queanbeyan Not commenced. Not commenced
Duplication of Princes Highway (Jervis Bay Road Intersection to Moruya), including bypass of Milton-Ulladulla Data at key sites along the Princes Highway were collected in June 2019.
The next steps will be to conduct further analysis, planning and other preparatory work.
Project site
In progress
Great Dividing Range long term solution The Connecting the Central West & Orana initiative has commenced to identify short, medium and long term solutions to improving connectivity for the region. In progress
Murray River Bridges Program Assessment of the 32 Murray River crossings has been carried out as a joint project between NSW and Victoria.
Project site
In progress
Sturt Highway improvements Development and delivery will be scheduled over the next five years.
Route Safety Review was completed October 2018.
Ongoing development of mass action treatments is underway.
In progress
Cobb Highway sealing missing links Sealing of the remaining sections of the Cobb Highway is in progress.
The NSW Government has prioritised this work with scheduled completion in 2022.
Project site
In progress
Main South Freight Rail Capacity Enhancements in collaboration with ARTC Not commenced. Not commenced
Newell Highway Improvements (in addition to those committed) All projects under this Initiative are in the planning stage including Coonabarabran widening, Boggabilla upgrade, Boggabilla to Goondiwindi safety enhancements and Tocumwal uncoupling bay.
Project site
In progress
Hume Highway Improvements A Route Safety Review was completed October 2018.
Development and delivery will be scheduled over the next five years.
In progress
Kidman Way improvements Not commenced. Not commenced
Inland Rail Intermodal Facility investigations Work underway with the Parkes Special Activation Precinct Project Team to provide multi-modal, integrated transport support in the investigation of appropriate locations for the private development of inter modal facilities in the Central West & Orana. In progress
New England Highway Improvements (Willow Tree to Armidale) The first stage of these improvements, between Uralla and Armidale, commenced in August 2018.
Works under development south of Tamworth are scheduled to commence in 2019/20.
Program site
In progress
New England Highway Improvements (Armidale to border) The first stage, between Uralla and Armidale, commenced in August 2018. In progress
Gwydir Highway Improvements (between Grafton and Glen Innes, Jackadgery) Not commenced. Not commenced
Kamilaroi Highway Improvements Early planning work to identify High Productivity Vehicle (HPV) access constraints is underway.
 
In progress
Oxley Highway Improvements (New England North West) Not commenced. Not commenced
Mt Victoria to Orange road corridor improvements to achieve travel time savings and road safety outcomes A Draft Corridor Plan has been completed.
Some projects are funded under the Saving Lives on Country Roads Program.
Program site
In progress
Henry Parkes Way improvements Upgrades to Henry Parkes Way are included in the Draft Orange to Condobolin Corridor Plan. In progress
Barrier Highway improvements (Dubbo-Broken Hill) Barrier Highway improvements (Dubbo-Broken Hill) are on track.
A draft Corridor plan is underway for completion in 2019-20.
In progress
Bells Line of Road improvements An ongoing program to improve road traffic efficiency on Bells Line of Road between Lithgow and Kurrajong Heights.
Project site
In progress
Extending Bathurst commuter rail to Orange This is under investigation within the Faster Rail Western Route Pre-feasibility Study.
Project site
In progress
Silver City Highway sealing missing links Work has been prioritised and scheduled for completion in 2022.
Project Site
In progress
The Wool Track sealing (Balranald – Ivanhoe - Cobar) Complete. Complete
Sturt Highway improvements Development and delivery will be scheduled over the next five years.
Route Safety Review was completed October 2018.
Ongoing development of mass action treatments underway.
In progress
Mitchell Highway improvements Work is in progress which includes lane and seal widening with clear zone works, safety measures, intersection improvements at highly trafficked locations, flood immunity works and asset maintenance. In progress
Regional Parking Guidelines These are currently being considered as part of a strategic approach to access to centres and interchanges. In progress

Six principles for Future Transport

The Future Transport 2056 Strategy is focused on six key principles for the future of mobility in the state, which together aim to positively impact the economy, communities and environment of NSW.

Read more